New Project

Which year's list this project belongs to
Target cost — actual costs are recorded in the Costs tab
Set 0 if no retention. Common: 10%
Common: 5%
When retention can be claimed back

New Payment / Claim

Upload Files

Photos, PDF or video · max 20 MB each · you can select several at once

New Variation Order

Positive = addition, negative = omission (e.g. -30000)

New Cost

Retention Release

Export

Import / Update Data

Accepts two file types:
  • CSV — same columns as the exported project list. Rows are matched by Project No., then by Project Name: matches update the project details, new rows create projects. If a new row has a "Received" amount, it is recorded as one combined paid payment; "Actual Cost" becomes one combined cost line; "VO Total" becomes one VO line.
  • JSON backup — restores every project from an exported backup (existing projects with the same ID are overwritten).
Tip: export the CSV first, edit it in Excel, then import it back.